Sanitary or not, a shell-and-tube exchanger is a pressure vessel, and in the United States that means ASME Boiler and Pressure Vessel Code Section VIII, Division 1. The code sets how the shell, heads, tubesheets and nozzles are designed, what materials may be used and at what allowable stress, how they are welded and by whom, what is inspected, and how the finished vessel is tested. A shop that holds an ASME certificate of authorization may apply the U-stamp to a vessel built under those rules, witnessed by an authorized inspector from an insurer or jurisdiction.
National Board registration adds a second step: the completed data report is filed with the National Board of Boiler and Pressure Vessel Inspectors, which assigns a permanent number stamped beside the U. Most states require it, and it is what an inspector looks up when the unit is installed or later sold. Canada runs its own system: a Canadian Registration Number issued per design by the provincial authority, required before the vessel is installed in that province.
Design begins with the maximum allowable working pressure and temperature on each side, which on a sanitary unit are set by the steam or utility pressure, the CIP pump head and the SIP steam temperature, not the product. From those the code fixes the shell wall, head thickness, nozzle reinforcement and tubesheet thickness, the last by the UHX rules that account for the tubes stiffening the sheet. Stainless allowable stresses are lower than carbon steel, so sanitary shells run slightly thicker for the same pressure. Welds are made to procedures qualified under Section IX by welders qualified to those procedures, and the authorized inspector checks material certificates, weld records and fit-up at hold points during the build.
When fabrication is complete the vessel is hydrotested, each side in turn, at 1.3 times its MAWP corrected for temperature, held while the inspector examines every joint for leaks. On a sanitary unit the test water is clean and the unit is drained and dried afterward so no residue is left on the product side. With the test passed, the fabricator stamps the nameplate with the U symbol, the MAWP and temperature each side, the serial number and the year, and completes the Form U-1 data report, which the inspector signs. That report is the legal record of the vessel and a copy goes to the buyer.
The fabricator files the signed data report with the National Board, which assigns a sequential number to the vessel and stamps it on the nameplate beside the U. The National Board keeps the report on file permanently. When a state inspector visits the plant, the NB number is what is entered in the state's vessel register and what is checked at each periodic inspection. Specify it; the cost is small and a missing number complicates every future inspection.
Canada requires a Canadian Registration Number for any pressure vessel before it is installed. The number is issued for a design, not a serial number: the fabricator submits drawings and calculations, done to ASME and CSA B51, to the provincial safety authority, which reviews and registers the design and issues a number whose decimal suffix identifies the province. A design registered in one province can be extended to others by a further filing. Fittings on the unit, including sanitary clamp connections and any valves shipped attached, must also be registered, either individually or under a category registration held by their maker.
CRN review takes weeks, and the unit cannot legally be installed until the number is issued, so the CRN is applied for when the order is placed, not when the unit is ready to ship.
State the MAWP and temperature each side, ASME Section VIII Division 1 with U-stamp, National Board registration, and the CRN province if the unit goes to Canada. Ask for the data report and the nameplate drawing as deliverables.
Call and talk it through with an engineer: 1-805-484-2992
Yes, on any unit that is steamed in place with the product side valved off. The arithmetic is simple: clean steam at 250 F fills the side at about 15 psig; when the steam is shut and the metal cools toward 100 F, the saturation pressure of the water left behind is under 1 psia, so the chamber sees close to 14 psi of external pressure. A thin polished head checked only for internal pressure may never have been checked for that. On small diameters a full-vacuum rating changes little or nothing in the metal; it simply gets calculated and recorded. Ask for FV on the product side of the nameplate drawing when SIP is in the duty, or when a hot product side can be valved off to cool.
Yes. The buyer can add witness points through an inspection and test plan, and pharmaceutical orders usually do. The authorized inspector's hold points are fixed by the code and the shop's quality manual; the buyer's are added on top, typically the final hydrotest, the borescope of product-side welds and the finish readings. Agree on the plan and the notice period when the order is placed; a closed head cannot be reopened for a witness nobody scheduled.
It must be stated correctly on the nameplate, although it almost never limits a 304L or 316L unit. MDMT is the lowest metal temperature at which the vessel may carry it's full rated pressure. Austenitic 304L and 316L are exempt from impact testing under Section VIII down to minus 320 F, so a glycol cooler at minus 20 F needs no special material, only the right number on the plate. A plate stamped at a default minus 20 F on a cooler later moved to minus 40 F brine is a finding at the next inspection. Give the coldest utility temperature the unit will ever see.
Low-chloride water, held briefly, then a full drain and dry; Section VIII itself sets no water quality limit. Pharmaceutical specifications commonly cap test-water chlorides at 50 ppm for austenitic stainless, and many ask for deionized or potable water with a stated limit. The reason is what happens after the test, not during it: a 304L bundle left wet with plant water for weeks on a dock can start crevice attack at the tube joints before the unit ever sees product. Our procedure drains, blows down and dries the product side immediately after the test, and the hydrotest report records the water used. If your QA has a chloride limit, put it on the order.
Yes. The NB number is permanent and the data report stays on file, so a relocated vessel is entered in the new state's register by number. A later owner can order a copy of the Form U-1 from the National Board. A stamped but unregistered vessel is harder to move: some states refuse to accept it, and late registration depends on finding the original data report and inspector. On a sanitary unit that may follow a product line to another plant, registration is cheap insurance.
Usually, if it is a true repeat: the CRN belongs to the registered design, not the serial number. A second unit built to the same drawings and calculations for the same province carries the same number without a new review. Change the tube count, the MAWP, the nozzle sizes or the clamp fittings and it becomes a revised design that must be resubmitted before the unit can be installed. A CRN issued in Ontario (suffix .5) also does not cover Alberta or Quebec without an extension filing, so name every province the design may go to.
How a sanitary exchanger is classified, assessed and CE marked under the Pressure Equipment Directive.
+ Learn More
A mechanical design standard and a verified sanitary mark: what each adds to the drawing and to the plate.
+ Learn More
Pressure codes, registration numbers and sanitary marks: what each is, who requires it, and where it goes.
+ Learn More